Contractor                                      Consultant                               Norfolk County

Xterra Construction Ltd.                G. Douglas Vallee Limited     Project Manager,

Ed Jones                                            Ryan Elliott, P.Eng                  Jeff Demeulemeester, CET

(226) 791-5335                                 (519) 426-6270                       (519) 426-5870 ext. 8087

Email: [email protected]      [email protected]

[email protected]

After-hours emergency 1-877-298-5888

Project Construction Budget – $335,000

Proposed Start Date – Mid-July 2024

Estimated Completion Date – End-September 2024

It is our intention to minimize the impact of this vital infrastructure work on the public and vehicular traffic.  If you have any questions or concerns regarding the work being completed, please reach out to the appropriate individual shown above.

Project Description

The Lot 21 Concession 13 Windham Culvert located on Fertilizer Road approximately 125m south of Wilson Avenue is scheduled to be rehabilitated.   See Attached Location Map.

The work will include the rehabilitation of the existing concrete box culvert ends, guide rail installation on the west side, and associated slope restoration.

Information for the Public

Traffic Management

During construction, the road will be closed to through traffic and a detour will be set up using Windham Road 13, Windham West ¼ Line Road and Windham Road 14.  Access to properties will be maintained with local access only.

Garbage and Recycling

Garbage and recycling collection services will remain the same.  The contractor may need to pick up and relocate garbage and recycling bins to an accessible location for waste management pick up.  Please have your garbage and recycling roadside by 7 a.m. the day of your regular collection schedule.  Municipal addresses should be labelled on all recycling bins so that they may be returned to the correct address.

 

Project Location

Map of work area