Project: Pine Ridge Estates Stormwater Pond Remediation SWM-PD1 - EIS-ES-25-11

Construction Dates: August 11, 2025 – October 31, 2025

Please note the estimated start date has been revised from September 1, 2025, to August 11, 2025.

Location: Port Dover, ON

This notice is to provide public notification of the pending remediation works at the Pine Ridge Estates stormwater management pond located at 15 Angler Avenue, Port Dover. 

Norfolk County has awarded a contract to Marbelle Group Inc. to undertake the remediation works including dewatering, wildlife management, sediment removal and disposal, and site restoration. A location map and site plan has been provided as an attachment to this notice.

Project Scope

The general scope of work may include, but is not limited to, the following activities:
•    Installation and removal of fencing, sediment and erosion controls
•    Pond dewatering 
•    Capture and relocation of fish and aquatic wildlife
•    Targeted excavation and removal of accumulated sediment (forebay only)
•    Disposal of sediment at an off-site location
•    Site restoration to original or better condition

Please note, this work is an interim preventative maintenance measure. This pond is scheduled for a more comprehensive cleanout in 2026.

Construction Schedule

The project has been awarded to Marbelle Group Inc. The contractor is expected to mobilize to the site on August 11th, 2025, with an anticipated completion date of October 31st, 2025.

Information for Homeowners

Transportation Impacts (Pedestrians | Cyclists)

Due to the size of the facility and restricted work area, this project will result in temporary restrictions/closure of the sidewalks and pathways adjacent to the stormwater management facility. For the safety and wellbeing of yourself and any pets, please stay out of the designated construction area during this project.

Driveway Access and On-Street Parking

The contractor is required to maintain access to all homes during construction.  There will be occasions when you may experience some delays, lack of service and inconvenience. Every effort will be made by the contractor to minimize these occurrences as well as communicate when they are to occur. Through this project, it is unlikely there will be any disruptions with respect to driveway/property access.
We do ask that you refrain from parking on the street during construction activities as this can delay things and prolong the construction period.

Lawn Sprinkler Systems

All work is to be completed on Norfolk County-owned property. It is unlikely that any private sprinkler systems will be affected by this project. However, we ask that if you have underground lawn sprinkler systems, please clearly mark the locations of sprinkler heads adjacent the stormwater management facility, road and/or sidewalk access.

Tree & Vegetation Removals

With every construction project comes the removal of some trees, shrubs or other vegetation for various reasons. Some are at the end of their life span, while others may be affected due to the constrained work site and the need for access by trucks and equipment. Trees deemed to present a hazard or conflict with the construction activities will be removed as part of this project. Norfolk County will evaluate the potential for appropriate tree planting opportunities after construction is complete.

Project Contact Information

Project Manager                    
Chris Dunn, C.E.T.                    
Manager, Stormwater and Drainage
Norfolk County        
 (519) 426-5870 x 8041
chris.dunn@norfolkcounty.ca

Contractor    
Peter Conte
Project Manager/ Estimator
Marbelle Group Inc.
289-228-2933
peter@marbellegroup.com

After-Hours Emergency
1-877-298-5888

If you have any comments, questions, or concerns about the Pine Ridge Estates Stormwater Pond Remediation Project, please contact Chris Dunn, Project Manager, at 519-426-5870 or 226-NORFOLK, extension 8041.

Thank you for your understanding.

This website uses cookies to enhance usability and provide you with a more personal experience. By using this website, you agree to our use of cookies as explained in our Privacy Policy.