Construction Dates:
- To begin Mid-April 2025 (Update: Substantial completion by August 29, 2025)
Location: Port Dover, ON
This notice is to provide public notification of the pending reconstruction and street scaping of Harbour Street, from the pier to the lift bridge, in Port Dover.
A location map has been provided as an attachment to this notice. The design drawings are available, along with additional information for reference on this page.
Project Description
Harbour Street – Pier to Lift Bridge
- Partial replacement of sanitary sewer and services
- Partial replacement of watermain and services
- Partial replacement of storm sewer and appurtenances
- New concrete curb and gutter
- New asphalt road surface and granulars
- New sidewalk and decorative concrete
- New decorative street lighting
- Implementation of street scaping features
Construction Schedule
The construction schedule will be finalized following Council's award of the contract. Construction is scheduled from mid-April to the end of July 2025. Substantial completion, including base asphalt placement, is required by June 11, 2025. Work will pause after June 11, with the contractor permitted to return on June 16, 2025, to complete final project items. The project is expected to be substantially completed by the end of August 2025.
Status Update – August 12, 2025
The Harbour Street Project is nearing completion. Remaining works include line painting, cross-walk printing, minor grading/sodding, and final sign installations. The decorative streetlights will be installed later this fall as the poles and lights are unfortunately on back-order. The final work will require some temporary (short-term) lane/road closures to facilitate the work. These are expected to be short in nature. We will make every effort to provide advance notice on these short-term closures however sometimes short-notice crew availability for small site works (like Harbour Street) requires us to be nimble and accommodating in effort to complete these final items in a timely manner. Please watch for and obey sign boards and barricades which will be used to inform road users of these temporary (short-term) closures.
The County continues to work with the Owner at 32 Harbour Street and the permitting authorities of the Department of Fisheries and Oceans (DFO) and Long Point Regional Conservation Authority (LPRCA) on the remedial works at the vacant lot near Harbour Street/Main Street. We hope to see the dilapidated sea-wall repaired later this fall and the lot brought back to level. When this work advances, some large equipment will need to brought into this site. We will provide advance notice when this work is ready to start.
Project Contact Information
The following is a list of contacts for the project:
Norfolk County
Matt Stam
Project Manager
Phone: 519-426-5870 or 226-NORFOLK, extension 8020
Email: matthew.stam@norfolkcounty.ca
During the construction of this project, it is our intention to minimize the impact on your everyday life. If any special needs or requirements routinely occur during a day or week, we need to be made aware of them in order that the necessary arrangements can be made so that these needs can continue to be met during construction.
If you have any comments, questions, or concerns about the Harbour Street Reconstruction and Street Scaping Project, please contact Matt Stam, Project Manager, at 519-426-5870 or 226-NORFOLK, extension 8020.
Tender Drawings
Contact Us
ServiceNorfolk
50 Colborne Street South
Simcoe, Ontario
N3Y 4H3
Phone: 519-426-5870 or 226-NORFOLK, extension 0