Big Creek 6th Concession Bridge Rehabilitation - EIS-ENG-26-52

Project Description

The Big Creek 6th Concession Bridge, located on 6th Concession Road approximately 0.40km west of Highway 59 near the village of Walsingham, which spans Big Creek, requires a major rehabilitation to the bridge structure.  

The work will include bridge deck replacement, bridge barrier and railing replacement, concrete repairs, road and asphalt restoration, and associated traffic control.

For reference, the project location map for the proposed work is located at the bottom of this notice.

Project Timeline

Proposed Start Date

week of May 11, 2026

Estimated Completion Date

early September 2026

Information for the Public

Traffic Management

In order to expedite the work in a safe environment, vehicular traffic control measures will be in effect. During the construction, 6th Concession Road from Highway 59 to Hazen Road will be closed to Local Traffic Only with complete closure at the bridge structure.  A detour will be in place using 7th Concession Road to the north via Hazen Road and Highway 59.

Construction Tender

The construction tender for this project was sent out to prequalified bridge construction contractors in February 2026.  Council has awarded this project to Urbanlink Civil Ltd., which was the low bid in the amount of $1,611.005.

We intend to minimize the impact of this vital infrastructure work on the public and vehicular traffic. If you have any questions or concerns regarding the work being completed, please reach out to Norfolk County’s Project Manager, noted below.

Project Contact Information 

Contractor
Urbanlink Civil Ltd.
Brandon Wallace
(289) 696-8094
brandonwallace@urbanlink.ca

Consultant 
G. Douglas Vallee Limited
Ryan Elliott, P.Eng
(519) 426-6270  
ryanelliott@gdvallee.ca

Norfolk County 
Project Manager, 
Jeff Demeulemeester, CET 
(519) 426-5870 extension 8087
jeff.demeulemeester@norfolkcounty.ca 

After-hours emergency 1-877-298-5888

Project Construction Budget

$1,611,005